Framing has started! The east-facing dormer is starting to take shape.


Underfloor radiant heat is in. Additions have insulation and subfloor too.

Still have an issue with the south wall along the property line -- does the entire wall, including the existing, have to be fire-rated? No overhangs within 3' of property line though, so the original south-facing overhang was torn down. Bummer.

We do have to order a new kitchen window, as the 45-degree bay we ordered will project within 3' of the property line. Our window guy is looking into a 30-degree bay, or maybe a 15-degree bow.

New problem with entry door. The custom door company's CAD drawing is considerably different than the door we were trying to imitate, an IWP (formerly Jen-Weld) model we hacked up to add glass area.


Re-order, start over. Another 10-12 weeks.